I started renovating both my living room and kitchen last week, both my kitchen and living room is a tip dust everywhere holes in the ceilings, wire hanging down , thought I could get it all done in two weeks just before the baby was due (9th Aug) as it happens the little nipper decided to come out on Friday I am well chuffed he weighed 5.14 lbs. I now have the task of getting every thing done in two weeks in the house. The misses and the boy will be staying at her mums whilst I will be staying at home. Before I started the project I thought I can do most things myself , like chase the walls for first fix electrical in the kitchen ( now I know why sparkies charge so much as its ****ing hard work) rip up the existing carpet in the living room, take off the existing wall tiles and floor tiles, strip out the kitchen , pipe work mods in the kitchen everything else like plastering , electrical, and kitchen fit will be done by others. I'm regretting ever starting this now, but it's too late to turn back now.
Here is my programme of works for the next two weeks :
w/c 30/7/13
Monday - Chase out approx 15lm of solid brick work for electrical conduits , 25mm depth (me)
Monday- take up living room carpet incl underlay - 7m x 3.5m (me)
Monday - Trip to the dump
Tuesday - finish of stripping off existing wall paper and coving to living room ( me)
Tuesday - rip out sink (me)
Wednesday - plaster living room (by others)
Wednesday-Pipe work mod in kitchen (by others)
Wednesday - 2nd fix electrical in kitchen , install two new sockets in living room (by electrician)
Thursday - finish re wiring kitchen and spotlights to living room (by others)
Thrsday - box in exposed pipework in kitchen (by others)
Thursday- plaster kitchen and finish plastering living room (by others)
Friday-screed kitchen 3mx4m (by others)
Friday - Install new front door (by others)
Friday - put up new coving in living room and kichen (BY ohers)
Saturday- rip out existing carpet to stairs (me)
Sunday mist coat kitchen (me)
Sunday, start mis coating Living room (me)
Monday start installing new kitchen units ( by others)
Monday - finish miscoating living room (me)
Tuesday- Install new skirting to living room (by others)
Tuesday - Ply out kitchen and install laminate flooring (by others)
Wednesday, start final finish paint to living room (me)
Thursday - Finish kitchen install (by others)
Friday - finish decorations (me)
Saturday build false chimney
Sunday -decorate false chimney
Monday- new carpet to stairs and living room
do you guys think its achievable?
Here is my programme of works for the next two weeks :
w/c 30/7/13
Monday - Chase out approx 15lm of solid brick work for electrical conduits , 25mm depth (me)
Monday- take up living room carpet incl underlay - 7m x 3.5m (me)
Monday - Trip to the dump
Tuesday - finish of stripping off existing wall paper and coving to living room ( me)
Tuesday - rip out sink (me)
Wednesday - plaster living room (by others)
Wednesday-Pipe work mod in kitchen (by others)
Wednesday - 2nd fix electrical in kitchen , install two new sockets in living room (by electrician)
Thursday - finish re wiring kitchen and spotlights to living room (by others)
Thrsday - box in exposed pipework in kitchen (by others)
Thursday- plaster kitchen and finish plastering living room (by others)
Friday-screed kitchen 3mx4m (by others)
Friday - Install new front door (by others)
Friday - put up new coving in living room and kichen (BY ohers)
Saturday- rip out existing carpet to stairs (me)
Sunday mist coat kitchen (me)
Sunday, start mis coating Living room (me)
Monday start installing new kitchen units ( by others)
Monday - finish miscoating living room (me)
Tuesday- Install new skirting to living room (by others)
Tuesday - Ply out kitchen and install laminate flooring (by others)
Wednesday, start final finish paint to living room (me)
Thursday - Finish kitchen install (by others)
Friday - finish decorations (me)
Saturday build false chimney
Sunday -decorate false chimney
Monday- new carpet to stairs and living room
do you guys think its achievable?